✆ +603-2935 9594
(Landline is currently unavailable due to technical reason. Please contact us via email / whatsapp. We apologise for the inconvenience  caused)

Category: CIPAA Case Update

Recommencing CIPAA Proceeding after the Adjudication Decision is being Set Aside?

The enactment of Construction Industry Payment and Adjudication Act 2012 allows the Contractor to recover payment from Employer speedily. In exceptional case, a CIPAA Adjudication Decision could be set aside under Section 15 of CIPAA 2012 where the Adjudicator had committed the following error: Section 15 of CIPAA 2012: Improperly procured adjudication decision An aggrieved party may apply to the High Court to set aside an adjudication decision on one or more of the following grounds: (a) the adjudication decision was improperly procured through fraud or bribery; (b) there has been a denial of natural justice; (c) the adjudicator has

Read More »

Ambit of CIPAA 2012 / “Construction Work” is to be construed widely & expansively

The enactment of Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012) is intended to provide remedies for the recovery of payment in the construction industry. However, the ambit of CIPAA 2012 is not merely restricted to the construction work in traditional sense. Section 4 of CIPAA 2012 defines ‘construction work’ as: ‘construction work’ means the construction, extension, installation, repair, maintenance, renewal, removal, renovation, alteration, dismantling, or demolition of: (a) Any building, erection, edifice, structure, wall, fence or chimney, whether constructed wholly or partly above or below ground level; (b)Any road, harbour works, railway, cableway, canal or aerodrome; (c)Any drainage,

Read More »

“Loss and Expense” Claim in CIPAA 2012

It is widely thought that a ‘loss and expense’ claim arises out of the employer’s delay is not claimable under CIPAA as a “loss and expense” claim is often regarded as special damages and not a payment for work done or services rendered claimable under CIPAA. In this case, the Kuala Lumpur High Court of Malaya clarified that an Unpaid Party / Claimant may claim for loss and expense arising from delays beyond its control in a CIPAA Adjudication Proceeding.   Syarikat Bina Darul Aman Berhad & Anor vs Government of Malaysia [2017] MLJU 2381 | [2017] MLJU 673 | [2017] 1

Read More »

Setting Aside of CIPAA 2012 Adjudication Decision by the Claimant / Unpaid Party

The enactment of Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012) allows the contractors / consultants to recover construction outstanding payment and resolve payment dispute speedily. However, there were cases where the Contractor’s / Consultant’s claims being wrongfully dismissed by the Adjudicator. In such scenario, it is previously thought that after the Unpaid Party’s / Claimant’s claim is dismissed by the Adjudicator, the Unpaid Party / Claimant can only proceed to recover the payment by commencing arbitration proceeding / court litigation, which often time could be very expensive and time-consuming. In this case, the High Court clarified and held

Read More »

CIPAA Adjudication Decision can only be set aside if the Breach of Natural Justice is Material and Decisive

A CIPAA Adjudication Decision is binding on the parties unless it is set aside pursuant to Section 13 of Construction Industry Payment and Adjudication Act 2012 (CIPAA), Under Section 15 of CIPAA, a CIPAA Adjudication Decision can be set aside if: (a) the adjudication decision was improperly procured through fraud or bribery; (b) there has been a denial of natural justice; (c) the adjudicator has not acted independently or impartially; or (d) the adjudicator has acted in excess of his jurisdiction. In this case, the Court held that not all allegation of breach / denial of natural natural justice can

Read More »

No positive award against Unpaid Party in CIPAA 2012! Non-Paying Party can only ‘zerorize’ claim

The introduction of Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012) allows an aggrieved contractor or consultant (known as Unpaid Party) to recover outstanding payment speedily against the Employer / Contractor (known as Non-Paying Party). In response to a CIPAA claim, the Respondent / Non-Paying Party may raise counterclaims / deduction / set-off to defend against the Claimant’s / Unpaid Party’s claim. What happen if the Respondent/ Non-Paying Party /Employer has a greater counterclaims / deductions / set-off against the Claimant / Unpaid Party? Can the Respondent / Non-Paying Party be allowed a positive claim against the Claimant /

Read More »

Contracting out of CIPAA 2012?

Following the enforcement of Construction Industry Payment and Industry Act 2012 (CIPAA) on 15 April 2014, the Asian International Arbitration Centre (AIAC) had recorded that there 89.28% of success rate where the CIPAA Adjudication Decision is awarded in the Claimant’s favour. Understandably, given the high success rate of CIPAA proceeding against the Employer, the Employer would be wary of CIPAA claim against them and the following questions arise: Can the Employer expressly exclude the operation of CIPAA 2012 in a construction contract? Would a contractual provision which expressly rules out the applicability of CIPAA 2012 is enforceable? In this case,

Read More »

No Certificate? No Problem! High Court ruled CIPAA can be based on uncertified claim

Bina Puri Construction Sdn Bhd v Hing Nyit Enterprise Sdn Bhd [2015] 8 CLJ 728 It is a common scene in the construction industry that the contract provides that the contractor’s rights to payment is subjected to the issuance of interim payment certificate and/or valuation of progress claim / interim payment claim. Such provision can also be found in the standard building contract such as PAM Contract, PWD Contract and CIDB Contract. As such, when Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012) first came into effect in 2014, one of the defence frequently raised by the Non-Payment Party

Read More »